Beginning April 14, 2013, San Jose Water Company will be conducting road work in Downtown Campbell, 10pm-6am, Sunday nights to Friday mornings. On some days, the work hours may be extended to 10am. Expect road closures during those hours. Water services will not be interrupted.
Why the hassle? San Jose Water Company will be retiring its 79 year old water main in Downtown Campbell and will replace the main with new pipeline along East Campbell Avenue from 3rd Street to the railroad tracks. The work will also include a water main replacement on Central Avenue from East Campbell Avenue to City Hall.
Beginning the week of April 21, 2013 there will be Mainline trenching on E. Campbell Avenue. This work will progress from east to west, block by block. It is anticipated that it will take approximately one week to trench per city block.
For more information, please read the SJ Water Company's notice; download the work map; or contact San Jose Water Company's Contractor, Lewis & Tibbitts, at 408-925-0220 or San Jose Water Company at 408-279-7900.